Estimating, Engineering & Processing
Control # 110 / Rev. / A
I. Purpose
To document the Estimating and Engineering process and to define
responsibilities.
II. Policy
The Estimating and Engineering process is critical to the success of PPC
and shall be conducted within the scope of the appropriate ISO standard, company and
customer requirements.
III. Responsibilities
The Engineering Manager has overall responsibility for this procedure.
Estimators, Engineers and Project Managers are responsible for compliance with this
procedure at the project, job, or process level.
Where appropriate the Quality Manager shall provide support and review prior to release of
manufacturing processes.
IV. Definitions
There are three basic types of manufacturing processed at PPC :
Prototype - This type of project or process is experimental in
nature. The process is controlled by the engineer and / or the customer. The Project
Manager for this job or process has overall responsibility for determining the required
inspection, test, process controls and documenting the results.
Production - This type of project or process is often referred to
as "Short Run" or ""Production work". This type of work includes
tooling, special machines, production and lower volume manufacturing and assembly work.
Assembly / Second Operation - Assembly / Second Operation is either
prototype or production for manufacturing with additional assembly process requirements.
Reference the assembly/second operation work instructions.
1 Reference
The work instructions for:
2 Tooling Requirements
Engineering shall design tooling that is functional and correct for the
use it was intended for.
Engineering shall provide proper instructions for qualifying and using said tooling.
All tooling shall be qualified prior to use in production or delivered to the customer.
3 Post Production Review
The Engineering, Department and Quality Managers are responsible for
monitoring the success of all design, engineering and manufacturing processes.
The Engineering Department and Quality Manager shall collect data on completed jobs,
project reports, customer needs, customer feedback and availability of new technology.